Martin Township Decides to Construct a New City Hall

Question 36

Short Answer

Martin Township decides to construct a new city hall. Based on the following data, prepare a statement of revenues, expenditures, and changes in fund balance for Martin Township's Capital Projects Fund. All transactions occur within the calendar year 2020.
a. The Fund starts and ends the year with a zero fund balance.
b. The Fund's financing sources for the city hall project were: long-term bond proceeds - $5 million; operating transfer from the General Fund - $2 million; state grant - $1 million; interest from the temporary investment of cash - $70,000.
c. Total outlays for constructing the new city hall were: construction costs - $7,200,000; design and construction supervision fees - $600,000.
d. City laws require that, whenever bonds are used, any remaining difference between total financing sources and construction costs must be transferred to the Debt Service Fund. Therefore, $270,000 was transferred to the Debt Service Fund.