Solved

The Difference Between the Standard Variable Overhead Cost for the Actual

Question 54

Multiple Choice

The difference between the standard variable overhead cost for the actual inputs of the measurement base and the flexible budget cost allowed for variable overhead based on outputs is known as the:


A) Variable overhead spending variance
B) Variable overhead efficiency variance
C) Fixed overhead budget variance
D) Fixed overhead volume variance

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge