Charlene Company has set labor costs at $24 per unit of output, based on 3 hours allowed to produce each finished unit. Last month, 1,500 direct labor hours were used, and 750 units of output were manufactured at a total cost of $36,000.
Required:
a. Determine the labor rate variance.
b. Determine the labor efficiency variance.
c. If the company used fewer direct labor hours than those reflected in the standards, which variance would be affected? Explain.
Correct Answer:

Verified
*$36,000/1,500 hours = $24
**$24 / 3 ho...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
**$24 / 3 ho...
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q37: If the actual level of activity for
Q38: Jasmin Company's budgeted sales were 2,000 units
Q39: Xing Pahang Products had the following variances
Q40: A standard cost of a product is
Q41: The variance that measures the amount of
Q43: The approach toward management that considers the
Q44: The net sales volume variance is a
Q45: Standard costs:<br>A) Indicate what it should cost
Q46: Excel Plumbing Company has three responsibility centers:
Q47: If the actual labor rate exceeds the