Multiple Choice
Which of the following is most appropriate for monitoring progress against plan?
A) Network diagram
B) Capacity loading graphs
C) Gantt chart
D) Flow diagram
E) None of the above
Correct Answer:

Verified
Correct Answer:
Verified