Multiple Choice
A document that isolates business drivers and restraining factors in an enterprise system implementation is called the:
A) KT plan
B) Project charter
C) Site readiness plan
D) Organization structure map
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q1: Building the enterprise around business processes as
Q2: Many of the concepts that underlie business
Q3: A document that deals with training issues
Q4: The document that examines technical transformations as
Q5: Reengineering an organization before implementing an enterprise
Q7: Even when a phased approach to implementation
Q8: A project team member who has a
Q9: A project team member who has a
Q10: A project team member who has a
Q11: Mapping company structure to the structure of