    In Comparing a Just-In-Time System with Material Requirements Planning, JIT
Solved

In Comparing a Just-In-Time System with Material Requirements Planning, JIT

Question 18

Question 18

True/False

In comparing a just-in-time system with material requirements planning, JIT is a push system of production control, whereas MRP is a pull system:

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q13: With which of the following manufacturing resources

Q14: A route sheet is a document whose

Q15: Small batch sizes are made economically feasible

Q16: Which of the following are the usual

Q17: Which one of the following types of

Q19: Autonomation refers to the design of production

Q20: The three modules in shop floor control

Q21: In lean production, which of the following

Q22: In a make or buy situation, the

Q23: The manufacturing engineering department in an organization

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines