Ambrose Wants to Create a Visualization to Show Senior Management

Question 76

Multiple Choice

Ambrose wants to create a visualization to show senior management the progress of each of the five projects that her team is working on. Each of the projects is made up of multiple tasks, so the chart will show a percentage completion of each project divided among the following subcategories: "complete," "in process,"
And "not started."
Which chart would help Ambrose visualize that information?


A) Heat map
B) Stacked bar chart
C) Histogram
D) Scatter plot

Correct Answer: