Risk Is Created Using the Waterfall Method When Developers Do

Question 52

Multiple Choice

Risk is created using the Waterfall method when developers do NOT receive feedback until project completion because of


A) changes in user expectations.
B) changes in requirements.
C) changes in business processes.
D) All of these answer choices are correct.

Correct Answer: