At the End of the Current Sprint, Astrid, the Product

Question 41

Multiple Choice

At the end of the current sprint, Astrid, the product owner, will seek feedback by presenting which scrum artifact to the end users?


A) Product backlog
B) Spring backlog
C) Product increment
D) All of these answer choices are correct.

Correct Answer:

verifed

Verified