Multiple Choice
Assume a facility is open 8 hours a day and requires an output of 600 units a day. The following tasks must be arranged as an assembly line:
-What should their takt time be?
A) 64 seconds
B) 72 seconds
C) 48 seconds
D) 60 seconds
E) Need more information to answer the question
Correct Answer:

Verified
Correct Answer:
Verified