A/An _____ demands knowledge of methods and techniques to ensure delivery of the project on time and on budget, and the ability to communicate project goals and requirements to the project team and to co-ordinate the workflows of everyone on the project team.
A) Project manager
B) Project sponsor
C) Account manager
D) Analyst
E) Developer
Correct Answer: