Multiple Choice
The impact on production lead time of an 8-hour constraint buffer:
A) Would be an additional 8 hours of production lead time inserted into the schedule.
B) Would depend on how full the constraint buffer was.
C) Would depend on whether or not the buffer decoupled the constraint from all disruptions.
D) Would be to remove 8 hours from the backward scheduling process.
Correct Answer:

Verified
Correct Answer:
Verified
Q33: A system's constraint could be a resource,
Q34: The consideration of the impact a decision
Q35: Disruptions that occur after the constraint<br>A) Cannot
Q36: Disruptions in productive systems<br>A) Can only be
Q37: A financial investment to increase the availability
Q39: The global performance measures that constraint management
Q40: The buffer used to ensure that components
Q41: Which of the following statements is true
Q42: Disruptions to systems can generally be measured
Q43: The phenomenon of increasing impact from statistical