The Impact on Production Lead Time of an 8-Hour Constraint

Question 38

Multiple Choice

The impact on production lead time of an 8-hour constraint buffer:


A) Would be an additional 8 hours of production lead time inserted into the schedule.
B) Would depend on how full the constraint buffer was.
C) Would depend on whether or not the buffer decoupled the constraint from all disruptions.
D) Would be to remove 8 hours from the backward scheduling process.