Multiple Choice
In rough-cut capacity planning, available hours are calculated by
A) Multiplying required capacity per unit by the quantity in the master production schedule
B) Multiplying the standard hours available by the hours actually used
C) Dividing actual output by expected output
D) Multiplying the actual hours available by the historical utilization and historical efficiency
Correct Answer:

Verified
Correct Answer:
Verified
Q21: Protective capacity<br>A) Tends to be in short
Q22: For many systems, the capacity of the
Q23: Under the demand chase approach to aggregate
Q24: Which of the following statements is true
Q25: In most business settings, capacity is defined
Q27: Which of the following statements identify the
Q28: Under level production aggregate planning, changes in
Q29: Match these items.<br>-Design capacity<br>A) When demand and
Q30: Capacity often has less an impact on
Q31: In services, achieving the demand-capacity match often