    Compute the Takt Time for 950 Units Demand Over a 40-Hour
Solved

Compute the Takt Time for 950 Units Demand Over a 40-Hour

Question 24

Question 24

Multiple Choice

Compute the takt time for 950 units demand over a 40-hour week.


A) .042 hours
B) 151.579 seconds
C) 23.75 seconds
D) 15.833 minutes

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q19: Five out of the seven categories of

Q20: One approach to determining the appropriate production

Q21: JIT and/or lean systems often focus on

Q22: An example of a "lean" technique that

Q23: A pre-requisite to understanding lean is recognizing

Q25: Explain the relationship between successful implementation of

Q26: The primary objective of lean systems is

Q27: The lean system philosophy of continuous improvement

Q28: Match these items.<br>-A workforce-focused waste reduction technique<br>A)

Q29: _ _ typically requires that equipment be

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines