Multiple Choice
If the MFE had a negative sign
A) The forecast method used inappropriate.
B) The distribution of randomness was skewed to the right.
C) The forecast tended to be too high.
D) Demand was higher than expected.
Correct Answer:

Verified
Correct Answer:
Verified