Multiple Choice
What does a PERT chart reveal?
A) the critical path for completing a project
B) the least-expensive path for completing a project
C) the number of workers needed for completing a project
D) the hours required by management to complete a project
Correct Answer:

Verified
Correct Answer:
Verified