Multiple Choice
A leak in the roof ruined part of the data needed to complete the high-low method calculation. The high point related to 50 units indicates a total cost of $1,840. Total fixed costs are estimated at $1,200. The plans are to produce 60 units in the current month. How much is the variable cost per unit?
A) $11.20
B) $12.80
C) $20.00
D) $64.00
Correct Answer:

Verified
Correct Answer: