Chandra Corporation has an observed and documented a learning curve of 90%, and production of units has increased from 10 to 20 units per week. If it is known that it takes 60 minutes to produce the 10th unit, what amount of time will it take to product the 20th unit?
A) 45 minutes
B) 50 minutes
C) 54 minutes
D) 60 minutes