Solved

Carmen Products Incorporated Plans to Produce 5,000 Units of Product

Question 6

Multiple Choice

Carmen Products Incorporated plans to produce 5,000 units of product in the coming month. At an expected wage rate of $25 per hour, budgeted direct labor wages total $75,000. What amount of budgeted direct labor time is required per unit of output produced?


A) 200 hours
B) 3,000 hours
C) 1.67 hours
D) 0.60 hours

Correct Answer:

verifed