Essay
Kando Manufacturing Ltd. produces two products, lawn mowers and power washers. Lawn mowers have a unit contribution margin of $75, and power washers have a unit contribution margin of $55. The demand for lawn mowers exceeds their production capacity, which is limited by available direct labour and machine hours. The maximum demand for power washers is 300 per week. Management desires that the product mix should maximize the weekly contribution toward fixed costs and profits.
Direct manufacturing labour is limited to 600 hours a week and 400 hours is all that the company's outdated machines can run a week. The lawn mowers require 1.5 hours of labour and 1 machine hour. Power washers require 2.5 labour hours and 2 machine hours.
Required:
Formulate the linear programming objective function and constraints necessary to determine the optimal product mix.
Correct Answer:

Verified
Note: P≤ 300 is not necessar...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
Note: P≤ 300 is not necessar...
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q44: First Image has a plant capacity of
Q45: Axle and Wheel Manufacturing is approached by
Q46: Lewis Auto Company manufactures a part for
Q47: Computer Products produces two keyboards, Regular and
Q48: Parker and Spitzer Manufacturing is approached by
Q49: A client in another province needs immediate
Q50: A company has two manufacturing facilities: one
Q51: Palmateer Industries makes an electronic component in
Q52: John Hatelak, a sales representative for a
Q54: The management accountant for the Awesome Candy