Multiple Choice
As a project is crashed from its normal duration to its optimal duration, ????.
A) The project's indirect cost is reduced
B) The project's direct cost is reduced
C) The duration of the project increases
D) Additional float is created
E) None of the above
Correct Answer:

Verified
Correct Answer:
Verified