True/False
In the case of design/build, the constructor acts as a general contractor with single-firm control of all subcontractors.
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q19: Match the type of schedule listed with
Q20: Match the description with the terms listed.Terms
Q21: Fair cost estimates represent the construction manager's
Q22: Match the description with the terms listed.Terms
Q23: Match the description with the terms listed.Terms
Q25: One major difference between equipment and material
Q26: A (An) ????clause is issued during a
Q27: Which of the following are the three
Q28: The construction manager is responsible for submitting
Q29: One advantage of a Design/Bid/Build delivery method