A swimming pool contractor builds a pool with a deep end 11 ft deep, instead of the 12 ft specified in the contract. Would specific performance be ordered? If not, how would damages be calculated?
Correct Answer:

Verified
When ordering specific performance, the ...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
When ordering specific performance, the ...