Solved

The Cost Functions Are Considered Reliable Within a Relevant Range

Question 78

Essay

The cost functions are considered reliable within a relevant range of 25,000 to 50,000 direct labor hours per month. The company expects to operate at 30,000 hours per month.
Actual results for February are as follows:
The cost functions are considered reliable within a relevant range of 25,000 to 50,000 direct labor hours per month. The company expects to operate at 30,000 hours per month. Actual results for February are as follows:    McIntire Inc. developed the following monthly cost functions for manufacturing overhead:    Required: (1) What are the following standard manufacturing overhead rates based on expected activity? (a) Variable manufacturing overhead (b) Fixed manufacturing overhead (2) (a) Prepare a flexible budget using the following headings: Budget at Overhead Cost VC/DLH Actual cost actual hrs. Variance (b) Which variances need to be investigated and what are some probable causes? McIntire Inc. developed the following monthly cost functions for manufacturing overhead:
The cost functions are considered reliable within a relevant range of 25,000 to 50,000 direct labor hours per month. The company expects to operate at 30,000 hours per month. Actual results for February are as follows:    McIntire Inc. developed the following monthly cost functions for manufacturing overhead:    Required: (1) What are the following standard manufacturing overhead rates based on expected activity? (a) Variable manufacturing overhead (b) Fixed manufacturing overhead (2) (a) Prepare a flexible budget using the following headings: Budget at Overhead Cost VC/DLH Actual cost actual hrs. Variance (b) Which variances need to be investigated and what are some probable causes?
Required:
(1) What are the following standard manufacturing overhead rates based on expected activity?
(a) Variable manufacturing overhead
(b) Fixed manufacturing overhead
(2) (a) Prepare a flexible budget using the following headings: Budget at
Overhead Cost VC/DLH Actual cost actual hrs. Variance
(b) Which variances need to be investigated and what are some probable causes?

Correct Answer:

verifed

Verified

(1)(a) Variable overhead rate = $1.85 (....

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions