Multiple Choice
Which of the following is a bar graph that measures planned and completed work along each stage of production by time elapsed?
A) Time and work chart
B) Gantt chart
C) Time and motion chart
D) Production and delivery chart
E) Gilbreth chart
Correct Answer:

Verified
Correct Answer:
Verified