Multiple Choice
The steps in analyzing the significance of gaps should include the following except:
A) establishing list the gaps
B) determining need and/or opportunity for each gap
C) judging feasibility of addressing gaps
D) determining which gaps competitors are now filling
E) selecting most important gaps to address and beginning to act
Correct Answer: