Demand is forecast for the next five months as 200,300,500,300,200.The production planner decides to adopt a level strategy,so over the next five months they should produce
A) 200,300,500,300,200.
B) 500,400,300,200,100.
C) 100,200,300,400,500.
D) 300,300,300,300,300.