Multiple Choice
Contours, Inc., quality auditors pull one part from the production line every 15 minutes. These parts are measured against the production print; any variation that is beyond acceptable levels is reported to the machine operators. Contours, Inc., is using ________ control.
A) feedforward
B) concurrent
C) feedback
D) concentric
Correct Answer:

Verified
Correct Answer:
Verified
Q36: Managers should do nothing if the variance
Q37: Because so many items had disappeared from
Q38: What are the major reasons why the
Q39: The Sarbanes-Oxley Act of 2002 requires senior
Q40: Provide a few examples for feedforward strategies
Q42: Sensitive, proprietary, and confidential information must be
Q43: _ refers to the process of monitoring,
Q44: Feedforward control is more popular and effective
Q45: Controlling is the process of monitoring, comparing,
Q46: Managers could choose to do nothing when