Multiple Choice
Which of the following are the steps in the business process management (BPM) cycle?
A) model processes; implement processes; assess results; create components
B) create components; model processes; implement processes; assess results
C) implement processes; create components; model processes; assess results
D) model processes; create components; implement processes; assess results
E) create components; implement processes; model processes; assess results
Correct Answer:

Verified
Correct Answer:
Verified