According to Brooks' Law, adding more people to a late project will ________.
A) guarantee efficiencies
B) speed up the project
C) create diseconomies of scale
D) reduce the need for coordination
E) reduce managerial overhead
Correct Answer:

Verified
Correct Answer:
Verified