Multiple Choice
During which of the following project planning activities do you use the information regarding tasks and resource availability to assign time estimates to each activity in the work breakdown structure?
A) Dividing the project into manageable tasks
B) Describing project scope, alternatives, and feasibility
C) Setting a baseline project plan
D) Developing a preliminary schedule
E) Developing a project scope statement
Correct Answer:

Verified
Correct Answer:
Verified