Multiple Choice
The extent to which the project is viewed as improving profits, customer service, etc., and the duration of these benefits best defines which of the following evaluation criteria?
A) Potential benefits
B) Resource availability
C) Technical difficulty or risks
D) Strategic alignment
E) Value chain analysis
Correct Answer:

Verified
Correct Answer:
Verified
Q70: The construction of an information system can
Q72: Using a discount rate of 14 percent,
Q73: To maintain consistency, the classification and ranking
Q74: Referencing the Management Issues section of the
Q75: Which of the following would be classified
Q77: The project charter reflects the best estimate
Q78: Which of the following would be classified
Q80: As a rule of thumb estimate, what
Q81: When comparing alternative methods for making information
Q86: Variable costs are costs resulting from the