Multiple Choice
A cost associated with an information system that can be measured in dollars and with certainty best describes:
A) economic cost.
B) tangible cost.
C) intangible cost.
D) one-time cost.
E) measurable cost.
Correct Answer:

Verified
Correct Answer:
Verified