What Does the Materials Requirement Planning (MRP) System Start with to Determine

Question 39

Multiple Choice

What does the materials requirement planning (MRP) system start with to determine inventory requirements?


A) Production scheduling.
B) Current inventory levels.
C) Projected budgetary allocation.
D) Sales forecasts.
E) Shipping rates and schedules.

Correct Answer: