Multiple Choice
The Beta distribution is used in project management to
A) calculate slack on activities not on the critical path
B) calculate the probability that a project will be completed within its budget
C) calculate pessimistic and optimistic activity times
D) determine which activity should be crashed
E) none of the above
Correct Answer: