Multiple Choice
An activity on a PERT network has these time estimates: optimistic = 2, most likely = 5, and pessimistic = 10. Its expected time is
A) 5.00
B) 5.33
C) 5.67
D) 17.00
E) none of these
Correct Answer:

Verified
Correct Answer:
Verified