menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Principles of Operations Management
  4. Exam
    Exam 3: Project Management
  5. Question
    An Activity on a PERT Network Has These Time Estimates
Solved

An Activity on a PERT Network Has These Time Estimates

Question 3

Question 3

Multiple Choice

An activity on a PERT network has these time estimates: optimistic = 2, most likely = 5, and pessimistic = 10. Its expected time is


A) 5.00
B) 5.33
C) 5.67
D) 17.00
E) none of these

Correct Answer:

verifed

Verified

Related Questions

Q1: If an activity whose normal duration is

Q2: A project whose critical path has an

Q8: _ is an organization formed to ensure

Q9: Which of the following statements about Bechtel

Q10: A partially solved PERT problem is

Q21: The phases of project management are:<br>A) planning,

Q38: Contract requirements state that a project must

Q79: Describe the differences between a Gantt chart

Q87: What are the earliest activity start time

Q117: Shortening the project's duration by deleting unnecessary

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines