An activity on a PERT network has these time estimates: optimistic = 1, most likely = 2, and pessimistic = 5. Its expected time is


A) 2.00
B) 2.33
C) 2.67
D) 8.00
E) none of these

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q3: What was the name of the construction

Q16: The network analysis method that allows activity

Q30: What are the three phases of a

Q39: In PERT analysis, the identification of the

Q54: The _ distribution is appropriate for calculating

Q75: A network consists of the following

Q77: Which of the following statements regarding PERT

Q79: WBS stands for which of the following

Q82: The main difference between PERT and CPM

Q85: Which of the following statements regarding CPM

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines