Essay
The network below represents a project being analyzed by Critical Path Methods. Activity durations are A=5, B=2, C=12, D=3, E=5, F=1, G=7, H=2, I=10, and J=6.
a. What task must be on the critical path, regardless of activity durations?
b. What is the duration of path A-B-E-H-J?
c. What is the critical path of this network?
d. What is the length of the critical path?
e. What is slack time at activity H?
f. What is the Late Finish of activity H?
g. If activity C were delayed by two time units, what would happen to the project duration?
Correct Answer:

Verified
(a) J; (b) 20; (c) A...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q5: Which of the following statements regarding PERT
Q17: In a PERT network, non-critical activities that
Q50: Slack is the amount of time an
Q91: Which of the following projects were completed
Q114: A project organization<br>A) is effective for companies
Q116: A project being analyzed by PERT has
Q117: If an activity whose normal duration is
Q118: Pirmin's Bike Shop is behind on
Q120: The critical path for the network
Q123: A diagram of all activities and the