The first unit of a product took 80 work days. The learning curve is estimated to be 90%. The time for the fourth unit will be about __________ work days and the time for the first four units will be about __________ work days.
A) 51; 250
B) 250; 51
C) 65; 285
D) 51; cannot be determined