Multiple Choice
PDCA, developed by Shewhart, stands for which of the following?
A) Plan-Do-Check-Act
B) Plan-Develop-Check-Accept
C) Problem-Develop Solution- Check- Act
D) Problem-Do-Continue-Act
E) none of the above
Correct Answer:

Verified
Correct Answer:
Verified