Essay
A consultant has been brought in to a manufacturing plant to help apply six sigma principles. Her first task is to work on the production of rubber balls. The upper and lower spec limits are 21 and 19 cm respectively. The consultant takes ten samples of size five and computes the sample standard deviation to be .7 cm and the sample mean to be 19.89 cm. Compute Cp and Cpk for the process. Give the consultant advice on what to do with the process based on your findings.
Correct Answer:

Verified
Cp = (21-19)/(6*.7) =.476
Cpk = min ( (2...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
Cpk = min ( (2...
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q28: A Type II error occurs when:<br>A)a good
Q52: What is the difference between the process
Q88: A part that connects two levels
Q89: A Cp of 1.33 indicates how many
Q92: The _ is the chief way to
Q94: A quality analyst wants to construct
Q95: The normal application of a p-chart is
Q121: Averages of small samples,not individual measurements,are generally
Q163: A c-chart is appropriate to plot the
Q213: The width of a bronze bar is