Essay
You have been asked to balance a flow shop assembly operation to achieve an output rate of 80 units per eight-hour day. Task times and precedence relationships are shown in the table below.
a. Draw the precedence diagram.
b. Determine the desired cycle time.
c. Determine the theoretical minimum number of stations needed.
d. Balance this line using most following tasks.
e. What is the efficiency of the line obtained in part d?
Correct Answer:

Verified
The precedence diagram appears...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q34: The central problem in product-oriented layout planning
Q40: Cyclone Appliances has developed a new
Q41: Takt time is<br>A) the total work time
Q42: _ is that element of balancing a
Q43: McDonald's "Made for You" kitchen system represents
Q44: The _ is a non-numeric method for
Q46: An electronics manufacturer makes remote control
Q47: A firm operates a flow shop
Q48: An insurance claims processing center has
Q50: Develop a solution for the following