Multiple Choice
The actual average observed time for a given job is 10 minutes. The performance rating is 80%, and allowances are set by contract at 10%. What is the time standard?
A) 8.80 minutes
B) 8.88 minutes
C) 10 minutes
D) 19.0 minutes
E) 19.8 minutes
Correct Answer:

Verified
Correct Answer:
Verified