Multiple Choice
A firm uses the pure chase strategy of aggregate planning. It produced 1000 units in the last period. Demand in the next period is estimated at 800, and demand over the next six periods (its aggregate planning horizon) is estimated to average 900 units. In following the chase strategy, the firm will
A) add 100 units to inventory in the next period
B) add 200 units to inventory in the next period
C) hire workers to match the 100 unit difference
D) lay off workers to match the 200 unit difference
E) implement a lower price point to increase demand
Correct Answer:

Verified
Correct Answer:
Verified
Q3: Which of the following is the term
Q4: Fred's Fabrication has the following aggregate
Q5: Because service firms do not inventory their
Q7: Which of the following uses regression to
Q9: Which of the following aggregate planning strategies
Q49: Describe the advantages and limitations of the
Q53: In aggregate planning, the amount of overtime
Q104: Graphical techniques are easy to understand and
Q119: Normally, the transportation model is used to
Q120: Explain the fundamental difference between the "capacity