    Given the Following Bill of Material
Solved

Given the Following Bill of Material

Question 38

Question 38

Multiple Choice

Given the following bill of material Given the following bill of material   If the demand for product A is 30 units, and there are 10 units of B on hand and none of C, how many units of part D will be needed? A)  3 B)  40 C)  70 D)  90 E)  110
If the demand for product A is 30 units, and there are 10 units of B on hand and none of C, how many units of part D will be needed?


A) 3
B) 40
C) 70
D) 90
E) 110

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q18: Which of the following statements best compares

Q33: MRP is generally practiced on items with

Q34: The extension of MRP which extends to

Q36: Wheeled Coach insists all of the following

Q37: The economic part period is a fraction

Q40: Explode the following Bill of materials assuming

Q41: The time-phased product structure, unlike the bill

Q43: Consider the following bill of material. Forty

Q58: The quantity required of a dependent demand

Q129: What is DRP?

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines