Multiple Choice
Each R requires 4 of component S; each S requires 3 of part T. The lead time for assembly of R is 1 week. The lead time for the manufacture of S is 2 weeks. The lead time for the procurement of T is 6 weeks. The cumulative lead time for R is __________ weeks.
A) 6
B) 9
C) 12
D) 18
E) 28
Correct Answer: