Essay
A very simple product (A) consists of a base (B) and a casting (C). The base consists of a plate (P) and three fasteners (F). There are currently 30 castings and 100 bases on hand. Final assembly takes one week. The casting has a lead time of three weeks. All other parts have one week lead times. There are no scheduled receipts. All components are lot-for-lot. The MPS requires 80 units of product A in week 5 and 120 in week 8. Produce the MRP for the upcoming eight weeks. Produce a list of all planned order releases.
Correct Answer:

Verified
Correct Answer:
Verified
Q70: The bill of material contains information necessary
Q71: Time fences divide that segment of the
Q72: By convention, the top level in a
Q73: A master production schedule contains information about<br>A)
Q74: In continuous (stock-to-forecast) operations, the master production
Q76: Consider the bill of material for
Q78: _ is a lot-sizing technique that generates
Q78: Which of the following statements regarding Wheeled
Q79: Each X requires 2 of component Y
Q80: When safety stock is deemed absolutely necessary,