The MPS calls for 120 units of Product M. There are currently 30 of Product M on hand. Each M requires 4 of Component N. There are 20 units of N on hand.
a. Calculate the net requirements for M.
b. Calculate the gross requirements for N.
c. Calculate the net requirements for N.
Correct Answer:

Verified
(a) 120 - 30 = 90; (...View Answer