The MPS calls for 50 units of Product A and 60 of B. There are currently 35 of Product B on hand. Each A requires 2 of Part C; each B requires 5 of C. There are 160 units of C available.
a. Calculate the net requirements for B.
b. Calculate the gross requirements for C.
c. Calculate the net requirements for C.
Correct Answer:

Verified
(a) 60 - 35 = 25; (b...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q1: Effective use of MRP and other dependent
Q55: While ERP may provide a strategic advantage
Q56: MRP is an excellent tool for scheduling
Q57: Which of the following regarding enterprise resource
Q61: Compare MRP in services to MRP in
Q64: In MRP, the number of units projected
Q65: Which portion of the master production schedule
Q84: What information is necessary for an operations
Q100: Distortion in MRP systems can be minimized
Q102: "Phantom bills" are bills of material for