Multiple Choice
A method of input-output control that uses a system of cards to limit the amount of work at a work center and also to control lead time and monitor backlog is
A) the assignment method
B) backward scheduling
C) forward scheduling
D) constant work-in-process or ConWIP
E) level material use
Correct Answer:

Verified
Correct Answer:
Verified